Week 49: Nov. 30 - Dec. 7, 2020 Last updated:   Dec. 3, 2020 8:40
Maintenance this week Date Time & Length Production resumes
520 MeV Tuesday, Dec. 1, 2020 starting at 08:30 for 7 hr + 2 hr start-up/tuning 17:30
ISAC Tuesday, Dec. 1, 2020 starting at 08:30
E-LINAC Tuesday, Dec. 1, 2020 maintenance in the AM, E-Hall will be locked up around 12 pm
                   
GROUP ACTIVITY Fault Report Work Permit Completed
ATG STF water package work (SAB3) 520 MeV C2020-12-01-7 y
Beamlines
Computing and Networking
Controls Replace T1/T2 PLC 520 MeV - C2020-12-01-1 y
Cryogenics and Vacuum Replace CSB:TP15A ISAC
Diagnostics ISIS toroid TNIM063 electronics commissioning 520 MeV - C2020-12-01-4 y
ISAC Target Hall ITE -> ITW ISAC - I2020-12-01-1 y
ISIS Regen cryopumps (TBD) 520 MeV - - not needed
Operations Sump checks All - - y
SCBCD & SCRM Tests 520 MeV - - y
1A -> 1B 520 MeV - - y
2A3/ITE  -> 2A2/ITW 520 MeV/ISAC - - y
Cycle 2C1 foil back to wire 520 MeV - - y
Remote Handling
RF
Safety
Site Services SAB3 pump check 520 MeV - - n
Mechanical, Civil/Structural, Electrical, FAS New cooling tower level sensor testing 520 MeV - no wp in progress
SAB3 subsurface drainage pipe clean-out 520 MeV - C2020-12-01-8 y
E-LINAC HAW system work (SAB3 access) 520 MeV/E-LINAC 12885/13200 A2020-12-01-2 y