Week 46: November 9 - 16 Last updated:   Nov. 10, 2020 16:24
Maintenance this week Date Time & Length Production resumes
520 MeV Tuesday, Nov. 10 starting at 08:30 for 7 hr followed by 2 hr start-up and tuning 17:30
ISAC Tuesday, Nov. 10 starting at 08:30
E-LINAC Nov. 9 - 11 E-Hall open Monday - Wednesday
ARIEL -
                   
GROUP ACTIVITY Fault Report Work permit Completed?
ATG
Beamlines Investigate and repair cyclotron vault water leak 520 MeV C2020-11-10-6 y - leak isolated for now, will be shutdown job
Computing and Networking
Controls Reboot CCSCS3 to fix 1A soft trips/stablility program readdev errors 520 MeV 13549, 13545 - not done, fault hasn't returned
ISAC Target Hall 2A2/ITW -> 2A3/ITE 520 MeV/ISAC y
ISIS Regen 061 520 MeV C2020-11-10-3 y
Check H2 supply in I1 520 MeV C2020-11-10-2 y
Operations Sump checks All - y
SCBCD & SCRM Tests 520 MeV - y
Retire Defeat#7101 - 2A3COL-TC3  520 MeV/ISAC 9993 - y
Investigate cyclotron vault water leak with Beamlines 520 MeV - y
2A2/ITW -> 2A3/ITE 520 MeV - y
Retire Defeat#8906 - 2A3M20 sum ratio for testing 520 MeV 13522 - y
Remote Handling
RF
Safety
Site Services SAB3 pump check 520 MeV - n
Mechanical, Civil/Structural, Electrical, FAS Cu-ALCW sidestream dissolved O2 sensor replacement (TBC) 520 MeV 13448 - n