Week 32: August 3 - 10 Last updated:   30-Jul-20
Maintenance this week Date Time & Length Production resumes
520 MeV Maintenance continued from Week 31, estimated to last until Friday, Aug. 7 (TBC). Jobs proposed but not confirmed are in italics. TBD
ISAC TBD
E-LINAC All week for E-GUN and RF HV conditioning TBD
ARIEL
                   
GROUP ACTIVITY Fault Report Work Permit Completed
ATG
Beamlines Continuation of shutdown job at M9/T2 (ongoing) 520 MeV -
Computing and Networking
Controls
Cryogenics and Vacuum LINDE troubleshooting and repair (Week 30 - ongoing) 520 MeV -
Diagnostics Load Ex1 foils (July 28) 520 MeV
Electrostatics and Power Supplies
Experimental Support
ISAC Target Hall Install and test interface relay between Safety System and Remote Handling storage vault door control module (August 6) ISAC
ISIS
Life Sciences
Magnets and Power Supplies Main magnet power supply diagnostics equipment install (date TBD) 520 MeV
Operations Sump checks All
SCBCD & SCRM Tests 520 MeV
EINJ/EACA safety critical tests (when cold)  E-LINAC
Remote Handling
RF Inspection of PAs (Week 30 -> TBD) 520 MeV C2020-07-24-5
IPA/TL directional coupler calibration measurements (TBD) 520 MeV
RF booster MRO (TBD) 520 MeV
Safety
Site Services Lift new west cooling tower onto pad (Aug. 5) 520 MeV/E-LINAC
Mechanical, Civil/Structural, Electrical, FAS Continuation of SAB3 VFD install (July 27 - TBD) [Electrical] 520 MeV C2020-07-24-1
Cooling tower replacement project (ongoing) 520 MeV/E-LINAC -
Cooling tower Cells C1/C2 maintenance 520 MeV C2020-07-27-4
SAB3 subsurface sump pump replacement 520 MeV/E-LINAC