Week 30: July 20 - 27, 2020 Last updated:   23-Jul-20
Maintenance this week Date Time & Length Production resumes
520 MeV Tuesday, July 21 No maintenance. 15 hr Beam development is scheduled starting at 08:30 followed by 1 hr start-up see below
ISAC Tuesday, July 21 No maintenance. 15 hr Cyclotron beam development is scheduled starting at 08:30 followed by 1 hr start-up see below
E-LINAC Shutdown
ARIEL Commissioning & Construction
                   
Due to the cyclotron vacuum system failure on Wednesday, July 21, there is unplanned maintenance time for the rest of week 30. Maintenance jobs confirmed to occur during this time are listed below (date range in brackets). Jobs proposed but confirmed are in italics. This list is dynamic. Also see the Week 31 tab.      
GROUP ACTIVITY Fault Report Work Permit Completed
ATG STF target swap and transfer (July 24) 520 MeV C2020-07-24-2 y
Beamlines Continuation of work at M9/T2 (shutdown job) 520 MeV
Computing and Networking
Controls Reboot CYCXFER IOC 520 MeV C2020-07-24-3 n - continue week 31
Cryogenics and Vacuum LINDE troubleshooting and repair (July 21 - ongoing) 520 MeV
Diagnostics
Electrostatics and Power Supplies Modify IB,356 power supply (July 24) 520 MeV C2020-07-24-4 y
Experimental Support
ISAC Target Hall 2A2M19 work [block removal] (July 23) ISAC y
ISIS
Life Sciences
Magnets and Power Supplies
Operations Sump checks All - y
SCBCD & SCRM Tests  (July 21) 520 MeV - y
Remote Handling
RF Inspection of PAs (July 24 -> Week 31) 520 MeV C2020-07-24-5
Safety
Site Services B3 Level Mechanical Services Room Inspection (July 22) 520 MeV C2020-07-22-6 y
Mechanical, Civil/Structural, Electrical, FAS Continuation of SAB3 VFD install (July 23 -> week 31) 520 MeV C2020-07-24-1
Install temp. AC unit on SAB2 520 MeV C2020-07-24-6