Week 20: May 12 - 18 Updated: 15-May-19
Maintenance this week Date Time & Length Production resumes
520 MeV Tuesday, May 14 09:30 - 17:00 (8 hr) + 2 hrs cyclotron start-up 19:00
E-LINAC As determined during the weekly E-LINAC meeting (Friday May 10) -
ISAC Shutdown until June 2019   Shutdown schedule: Collection-9271 Collection-9271
                   
GROUP ACTIVITY Fault Report Work Permit Completed
ATG Adjustment of STF target holder manipulator 520 MeV - C2019-05-14-5 Y
Beamlines
Controls Update access control files on Cyc EPICs IOCs 520 MeV - C2019-05-14-6 Y
0667 ToF Clock module replacement 520 MeV 12237 C2019-05-09-4 Y -  issue now with Diag equip
CCSCS3 GEC0 CAMAC interface move (CCSCS3 to go down for ~30 min) 520 MeV C2019-05-14-6 Y -  fault still present
Diagnostics T1 protect troubleshooting - access top of module for testing in situ  520 MeV 11796 C2019-05-14-7 Y - fault still present
Troubleshoot ToF readback in the DCR 520 MeV 12237 - Not done
Remove 1AM9.5 electronics (not used) and install 1AM6.9 (new BPM) electronics 520 MeV - C2019-05-14-13 Y
ISIS ISIS HV ballast resistor and relay tests 520 MeV - C2019-05-14-2 Y - SCBCD commissioning done
Check H2 520 MeV - C2019-05-14-1 Y
cryo #166 & 030 regen 520 MeV - C2019-05-14-4 Y
Experimental Support & Life Sciences M20: Check the cryopumps inside the service cave 520 MeV - C2019-05-14-3 Y
Transport of radioactivie waste to SAB3 tunnel 520 MeV - C2019-05-14-10 Y
Magnets and Power Supplies
Operations Weekly SCRM and SCBCD tests 520 MeV - - Y
Sump checks All - - Y - SAB3 done
Repeat T1 target scans @08:30, take T1 profile measurement 520 MeV - - Y
RF Low Level Controls investigation of VSWR trips 520 MeV - - Y
Add vault leak detectors to VSWR monitor interlocks 520 MeV - C2019-05-14-12 Y
RF tuner loop optimizations (starting at 13:00 w/ RF ON) 520 MeV - - Y
Install leak detector in SAB3 under Tx line 520 MeV - C2019-05-14-12 Y
Safety Sample and assay SAB3 active sump 520 MeV - - Y - SAB3 done
Site Services Inspect Cu-ALCW deionizer loop filters 520 MeV - C2019-05-14-11 Y
(Mechanical, Civil/Structural, Electrical, FAS) Weekly routine check up and lubrications in SAB3 520 MeV - C2019-05-14-11 Y
Craning activities over the cyclotron vault  520 MeV - - Y - transformer off vault roof
Uncover top of T1 for target module testing 520 MeV - C2019-05-14-7 Y
1A Targets
Remote Handling